Week 10: Sewerage & Water Installation
This week saw major progress beneath the surface as sewerage and water infrastructure was laid throughout the construction site at Marina Bay.
Week 9: Resort Villa Construction Begins
This week marks the true start of vertical construction at Marina Bay Lombok, with our crews officially breaking ground on the first resort-side villas.
Week 8: Worker Camp Completion & Government Talks
This week at Marina Bay Lombok marked a turning point both on the ground and behind the scenes.
Week 7: Site Scanning & Pegging
Week 7 at Marina Bay Lombok was all about turning plans into reality. Our surveyors spent the week conducting detailed land scans and pegging out the site; a key milestone in transitioning from design to delivery.
Week 6: Construction Commences
This is the moment we’ve been building toward; construction is officially underway at Marina Bay City.
Week 5: Power Installed & Signage Goes Up
Week 5 brought some of the first big visual changes to the site at Marina Bay Lombok, with two key upgrades now complete; power infrastructure and project signage.
Week 4: Drilling & Bore Testing
In Week 4, the team at Marina Bay Lombok carried out extensive on-site drilling to support structural planning and assess groundwater availability.
Week 3: Site Survey & Planning
Week 3 at Marina Bay Lombok focused on the detailed site survey and masterplanning for the villa development zone.
Week 2: Geoelectric Scanning Underway
This week at Marina Bay Lombok, geoelectric scanning was carried out across the site to assess soil conditions and underground water flow ahead of foundational work.
Week 1: Road Clearing
The journey officially began this week at Marina Bay Lombok, with road clearing works underway across the development site.